cancel
Showing results for 
Search instead for 
Did you mean: 
sheena11
Occasional Member - Level 1

expense claim

Dear Team,

For the upcoming travel, hotel accommodation has been 100% paid from my credit card and an expense is open in SAPConcur which rings an alert every week to claim that open. When i tried to do that, i got an alert mentioning, you cannot claim future dates expenses.

Is it ok, if i submit this claim post the trip and if not what is the other way ? 

Thanks & BR, Sheena

4 REPLIES 4
PoojaKumatkar
Frequent Member - Level 1

Hi @sheena11 ,

 

Usually request module is used to take future dated travel pre-approval and Expense module is used to claim past dated expenses. Hence you are getting error for future dated expenses while creating expense report. It is Concur's standard audit rule. Therefore, it is expected to submit expense reports post travel. 

 

If this answers your query, then please mark solution as accepted.

 

 

Thanks!
Regards,
Pooja
sheena11
Occasional Member - Level 1

thanks @PoojaKumatkar  for the quick response. However, if i wait to submit the claim post my travel, are you sure that there are no escalations  which will be triggered to my manager mentioning you have an open claim which you have not claimed for >30days ? 

PoojaKumatkar
Frequent Member - Level 1

Hi @sheena11 ,

 

As per my understanding you are talking about unsubmitted credit card transactions email reminders and in your case those transactions are future dated if my understanding is correct. Can you please confirm transactions are created for which date?

 

Such reminders are configured in system just to remind end users to timely submit their expenses. Now it totally depends on how your system is configurated. 

 

Ex. if you have not submitted your expenses X number of day then system will try triggering email reminders. Ex. 30 days. From 31st day user will start receiving email reminders. 

 

Here, in your case two things are overlapping, credit card transactions are created for future dates and expenses are restricted from submission for future dates.

 

Option 1: If future date alert message is just a yellow warning message, then you can still submit your expenses as system will not restrict you.

Option 2: But if you are getting red alert message (restrict submission) then you have to wait until credit card transaction date gets pass or can submit post trip as there will be no choice left.

 

Regarding notification to the manager, It is just a one of the functionality to mark in email reminders to keep them inform. Even if they reach out to you then, you can tell them due to future date restriction you are not able to submit your report.  

Or 

You can also reach out them now and take their suggestion what to do in this scenario. 

 

 

 

Thanks!
Regards,
Pooja
KevinD
Community Manager
Community Manager

@sheena11 I looked at your report. It is odd that the hotel charged you fully for a stay you haven't even completed yet. Due to the future dated expenses rule, you will need to wait until your stay is complete so that the future dated message goes away. 

 

I don't believe your manager will receive any notice about you having an unsubmitted claim. Also, managers only receive notices for credit card transactions of their employees that are over 42 days old. Since the hotel charged you on December 3, it will probably age past 42 days before you complete your trip. I would suggest letting your manager know that they will receive a notice.

 

Also, I would speak with your manager about what the company policy is when a hotel charges you for the complete stay at the time of booking. You don't want to wait too long to submit, but since Hotel expenses require itemization and you cannot put future dates, how do you submit this in a timely manner. 


Thank you,
Kevin
SAP Concur Community Manager
Did this response answer your question? Be sure to select “Accept as Solution” so your fellow community members can be helped by it as well.