Can service dates on a PO be changed after it's approved and no invoices have been applied? 

3 REPLIES 3
KevinD
Community Manager
Community Manager

@Manav has the PO been transmitted or not? Also, I am looking in our test site and I don't see any service date fields. Could you take a screenshot of this for me please?

 

From what I see in our test site, very few things can be edited once approved and waiting for transmission.


Thank you,
Kevin Dorsey
SAP Concur Community Manager
Did this response answer your question? Be sure to select “Accept as Solution” so your fellow community members can be helped by it as well.
Manav
Occasional Member - Level 2

@KevinD It's an approved PR converted to a PO and transmitted. Apologies, the service dates are entered when submitting the PR.

Manav_0-1672245206062.png

 

KevinD
Community Manager
Community Manager

@Manav if transmitted, then I think those dates are locked.