mtahir_1974
New Member - Level 1

Addition Of WBS

I am new to Concur. 

 

I need your help in adding new WBS to the existing projects. please advise how to add new WBS in SAP Concur.

 

Thank you

2 REPLIES 2
KevinD
Community Manager
Community Manager

@mtahir_1974 Hello there. First thing...do you have access to the List Management screen from Expense Administration? That is the first thing I need to know. I'll await your reply.


Thank you,
Kevin
SAP Concur Community Manager
Did this response answer your question? Be sure to select “Accept as Solution” so your fellow community members can be helped by it as well.
PoojaKumatkar
Super User
Super User

Hi @mtahir_1974 ,

 

To add WBS in existing project list you need to follow below navigations:

 

Role required - Expense Configuration Administrator (restricted/unrestricted)

 

Home >> Under Administration section >> click Expense option >> List management >> Search and Open existing used Org Hierarchy/project list and add new WBS as shown below:

 

 

PoojaKumatkar_0-1760944381645.png

PoojaKumatkar_2-1760944744551.png

 

 

If this answers your query then please mark solution as accepted.

Thanks!
Regards,